1) The installation of the fixing parts starts 8 hours after the insulation board is pasted, and is completed within 24 hours thereafter. Use the percussion drill to drill the hole according to the design requirements. The hole diameter is 10, the depth of drilling into the base wall is about 60, and the depth of anchoring the anchor into the base wall is about 50 to ensure firmness and reliability.

2) The number of fixed parts is set for each board.

3) Self-tapping screws should be squeezed tightly and the engineering plastic expansion nail caps should be neatly or slightly screwed into the surface of the composite foamed cement board to ensure that the tails of the expansion nails are screwed back to make them fully anchored to the base wall.